PHOTOS: The Denning Drive Complete Streets Project Phase One to be Complete by End of January



Phase 1 of the Denning Drive Complete Streets project from Orange to Fairbanks Is substantially complete and the only remaining items are installation of trees, irrigation and landscape along with about 100 feet of sidewalk and cleanup. The permanent road striping will be completed following cure period of the asphalt which is typically a month or so. The adjoining property owners are pleased with the improvements. Phase 2 (from Fairbanks to Webster) will begin by end of January and be substantially complete by June 1st.